Earned Value Management Calculator
Result
Cost Performance Index (CPI) 0.82
Schedule Performance Index (SPI) 0.90
Cost Variance (CV) -Rs 2,000
Schedule Variance (SV) -Rs 1,000
Estimate at Completion (EAC) Rs 61,111
Earned Value Management Calculator is a financial calculator that helps you calculate core earned value metrics (CV, SV, CPI, SPI, EAC) for project cost and schedule control. The formula used is: CV = EV − AC; SV = EV − PV; CPI = EV ÷ AC; SPI = EV ÷ PV; EAC = BAC ÷ CPI. Enter planned value (PV), earned value (EV), actual cost (AC) and budget at completion (BAC) in your local currency.
Formula
CV = EV − AC; SV = EV − PV; CPI = EV ÷ AC; SPI = EV ÷ PV; EAC = BAC ÷ CPI
- Formula: CV = EV − AC; SV = EV − PV; CPI = EV ÷ AC; SPI = EV ÷ PV; EAC = BAC ÷ CPI
- Enter planned value (PV), earned value (EV), actual cost (AC) and budget at completion (BAC) in your local currency.
Example Calculation
Enter your values and the calculator applies the formula (CV = EV − AC; SV = EV − PV; CPI = EV ÷ AC; SPI = EV ÷ PV; EAC = BAC ÷ CPI) and shows the results below. Change any input to update the result instantly.
Frequently asked questions
What is the Earned Value Management?
The Earned Value Management Calculator helps you calculate core earned value metrics (CV, SV, CPI, SPI, EAC) for project cost and schedule control. Enter planned value (PV), earned value (EV), actual cost (AC) and budget at completion (BAC) in your local currency.
When should I use this calculator?
Use this calculator whenever you need a quick, accurate result for calculate core earned value metrics (CV, SV, CPI, SPI, EAC) for project cost and schedule control.
What should I enter?
Enter planned value (PV), earned value (EV), actual cost (AC) and budget at completion (BAC) in your local currency.
How accurate are the results?
Results are estimates based on the stated formula and assumptions. Verify against your own figures or an authoritative source before acting on them.
How can I verify the calculation manually?
Apply the formula (CV = EV − AC; SV = EV − PV; CPI = EV ÷ AC; SPI = EV ÷ PV; EAC = BAC ÷ CPI) and work through the numbers step by step. If your result differs, re-check units and rounding first.